Public procurement: Dredging channel port of Oranjestad

Published on July 10, 2017

According to specifications: KD No. 1-2017.

Short description of the work
“Dredging of loose material” maintenance dredging “from the channel port of Oranjestad Building a quay wall at Barcadera. The dredging and deposit of dredged material for the land reclamation at Barcadera. ”

Duration of execution: 60 working days.

The specification is available at Aruba Ports Authority N.V. from July 10, 2017, against payment of Afl. 1500, =.
The payment must be met by the cashier of the Aruba Ports Authority.
The public documents are available for inspection from July 10, 2017 at the Aruba Ports Authority N.V.

Information will be provided on August 2, 2017 at 10.00 am. at the Aruba Ports Authority N.V.
The information note is ready on August 4, 2017 and is from that day available from the Aruba Ports Authority N.V.
The public tender will take place on August 25, 2017 at 11.00 am. at the office of the Director of the Aruba Ports Authority N.V.
The L.O.A. L.B. 1996 No. 58 is applicable to this tendering.
The supervision will be conducted by the Aruba Ports Authority N.V./KD Consult
The tender price will be maintainance for a period is 60 days.

The tenderer must submit the following requirements upon registration:
1. Proof of registration in the register of the Chamber of Commerce;
2. A list of subcontractors to be used;
3. Specification of tender price;
4. The other documents mentioned in the specifications

Scroll To Top